Project Scope
This project was the first Nephron Pharmaceutical manufacturing plant utilizing a a high bay rack storage system. The CENTRIA 4” Versawall Panels were installed directly onto the rack storage structural girts covering the automative 120’ high machine shell. This 70,000 SF of panels was installed 13 weeks.